1. 400 kV Cable Project Aarhus-Aalborg – General Outline
1.1 Introduction
Electricity cannot be stored. Production must correspond to consumption, placing
demands on the transmission grid. Denmark’s geographical location between the
European continent and the rest of Scandinavia is of considerable strategic importance
as far as electricity transmission is concerned.
Map of Europe
Denmark is situated between two large electricity transmission grids:
Zealand and the other islands in eastern Denmark are together with Norway, Sweden
and Finland connected in one synchronous grid, while Jutland and Funen are
connected to the Central European grid.
Map of Denmark, the transmission grid with international interconnections. Figure
37
Eltra is responsible for the overall security of supply and plans, builds, operates and
owns the transmission grid. This film focuses on the western part of Denmark for
which Eltra is responsible.
The transmission grid is a 400 kV grid of ring connections which are connected to the
primary power stations in Aabenraa, Fredericia, Esbjerg, Odense, Aarhus and Aalborg
as well as to Germany. The connections to Norway and Sweden are d.c. connections.
There are two important nodes in the